Coca Codo Sinclair Dam

Dam on the Coca River in Napo Province, Ecuador
You can help expand this article with text translated from the corresponding article in Spanish. (February 2021) Click [show] for important translation instructions.
  • Machine translation, like DeepL or Google Translate, is a useful starting point for translations, but translators must revise errors as necessary and confirm that the translation is accurate, rather than simply copy-pasting machine-translated text into the English Wikipedia.
  • Do not translate text that appears unreliable or low-quality. If possible, verify the text with references provided in the foreign-language article.
  • You must provide copyright attribution in the edit summary accompanying your translation by providing an interlanguage link to the source of your translation. A model attribution edit summary is Content in this edit is translated from the existing Spanish Wikipedia article at [[:es:Coca Codo Sinclair]]; see its history for attribution.
  • You may also add the template {{Translated|es|Coca Codo Sinclair}} to the talk page.
  • For more guidance, see Wikipedia:Translation.
Dam in El Reventador
0°08′17″S 77°27′11″W / 0.138°S 77.453°W / -0.138; -77.453StatusOperationalConstruction began2010Opening date2016Construction costUS$2.6 billionBuilt bySinohydro-Andes JVDam and spillwaysType of damConcrete-face rock-fillImpoundsCoca RiverHeight (foundation)31.8 m (104 ft)Length160 m (520 ft)Commission date2016Hydraulic head620 m (2,030 ft)Turbines8 x 187.5 MW Pelton turbinesInstalled capacity1,500 MW (2,000,000 hp)

The Coca Codo Sinclair Dam is a hydroelectric dam in Ecuador. It is located on the Coca River in Napo Province, 100 kilometres (62 mi) east of Quito.[1][2] It is the largest energy project in Ecuador.[1] The dam was constructed by Chinese engineering firm Sinohydro Corporation for $2.25 billion.[3]

The plant became fully operational in November 2016.[4] It has a capacity of 1,500 megawatts.[3][5]

Funding of dam

Ecuadorian and Chinese flags inside the hydroelectric power plant.

Over the years, China provided $19 billion in the form of loans to Ecuador for the construction of "bridges, highways, irrigation, schools, health clinics and a half dozen dams" including the Coca Codo Sinclair dam.[2] According to an article in The New York Times, Ecuador repays its debt to China by providing China with oil "at a discount". By 2018, this meant that China imported 80 percent of oil produced in Ecuador. The loan from China’s Export-Import Bank for the Coca Codo Sinclair Dam amounts to $1.7 billion with an interest rate of 7% interest over 15 years which is $125 million a year in interest alone.[2]

Post construction

In December 2018, 7,648 large and small cracks were identified in the generator hall and in surrounding equipment.[2] The cracks were first discovered in 2014 but the full extent of them is unknown as a thorough assessment would include deconstructing portions of the power plant which is cost prohibitive.[6]

After the dam became operational, its reservoir caused regressive erosion upstream and water absent of sediment released from the dam has caused high rates of erosion downstream which likely led to two oil spills after pipelines along the river lost their footings. Downstream erosion, if left unchecked would undermine the dam and other oil infrastructure by 2022.[7] Additionally, the erosion resulted in the destruction of San Rafael Falls further downstream and the resulting headward erosion is destroying the village of San Luis.[8]

References

  1. ^ a b "Coca Codo Sinclair Hydroelectric Project". power-technology.com. Retrieved 24 December 2018.
  2. ^ a b c d Casey, Nicholas; Krauss, Clifford (24 December 2018). "It Doesn't Matter if Ecuador Can Afford This Dam. China Still Gets Paid". The New York Times. Retrieved 24 December 2018.
  3. ^ a b "Ecuador". International Hydropower Association. May 2017. Retrieved 2019-03-26.
  4. ^ Ingram, Elizabeth (November 21, 2018). "TUV SUD to determine solutions to distributor cracks at Coca Codo Sinclair hydroelectric plant". Hydro Review. Archived from the original on 2018-12-29. Retrieved 2019-03-26.
  5. ^ Harris, Michael (December 15, 2014). "At least 13 killed by collapse at Ecuador's Coca Codo Sinclair hydropower plant". Hydro Review. Archived from the original on 2019-03-27. Retrieved 2019-03-26.
  6. ^ "Ecuador's largest hydroelectric plant is full of cracks; investigators blame Chinese contractor – CuencaHighLife". cuencahighlife.com. Cuenca High Life. 15 November 2018. Archived from the original on 10 June 2023. Retrieved 29 May 2020.
  7. ^ "Massive erosion likely due to hydropower dam causes oil spill on Ecuador's Coca River". Mongabay Environmental News. 6 May 2020. Retrieved 29 May 2020.
  8. ^ Journal, Ryan Dube and Gabriele Steinhauser | Photographs by Isadora Romero for The Wall Street (20 January 2023). "China's Global Mega-Projects Are Falling Apart". Wall Street Journal. Retrieved 2023-01-21.